Monday, May 16, 2011

Small craft build(male strong back)

At the end of last term we were spilted in to 3 groups cause we are buliding 3 different boats in this term
2.5M dinghy , 4M dory, and 2.4M Pippi.My group is making 3.4M dory.





Today, we just started Small Craft build and starts to make 4M dory
and the time we have is 6weeks and 2days.
We talked about timeline and brainstorming information about dory.






The 1st thing what we've done was to find the table  for 4M dory but, all the table wasn't long enough so we had to extend the table by our selves.After measuring height, width , and extension length we could make our cutting list.
-600*2          -810 *4 legs     -4screw blocks
-2braces        -1000*2 Extension



 we used pine whole length of 2800, width of 150 and height of 50.
After dressing and cutting the pine in to a piece,the rest of our group have finished drilling male strong back to the floor by using screw blocks.Also they made table exactly parellel  by using label.

1 comment: